Update On Third Mainland Bridge Repairs (Week 21)




 It’s week 21!

This week continues with the removal of old joints on the second lane using the hydro demolition robot to cut the concrete open and remove debris. 

We lost some time but we are working to ensure we finish on schedule. 

 